Freedom Park Under Progress

Freedom Park Under Progress

 

 

1)Utility Duct 850m/850m completed. 
2)Pathway-GSB laying is completed 750m/750m. and DLC was laid 750/750m
3)Stage-2  approach ramp has been cast and platform RCC slab completed. 
4)Stage-1  Plinth beam casting is completed. 
5)Stage-3 RCC platform has been cast. 
6) Mural wall top beams have been cast. 
7)Toilet block: Internal and external plastering is in progress. 
8) Pre cast cover slabs placing is in progress. 
9) Both sides Kerb stone fixing work is under progress 700m/750m.
10) Lowering and leveling  work for parking area is in progress.
11) Granite sets laying for pathway has been completed. 
12) Earth filling for landscaping is in progress.
13) cable tray fixing and  cable laying works have been completed.
14) GI flat fixing work is completed. 

Physical progress: 67%
Financial progress:33.80%