Development of Tank Mohalla park in Shivamogga

Pathway, Gym equipment`s, Poles and Horticulture

Cost as Per SCP Work Order Cost Implementation Duration Date Of Completion Agency
0.45 Cr 0.46 Cr 6 Months 28.02.2019  
Executive Engineer Assistant Executive Engineer  Assistant Engineer    
Ganesh  Priyadarshini H S Chethan S P